|
|
||||||
|
In July 2003, the Public Service Commission of Wisconsin (PSCW) and the state's Department of Natural Resources (DNR) issued their final Environmental Impact Statement (EIS) for the Elm Road Generating Station. The EIS was conducted under guidelines of the Wisconsin Environmental Policy Act (WEPA), which are modeled on the federal National Environmental Policy Act (NEPA) guidelines. The agencies' decision to conduct an EIS was not the result of an evaluation and conclusion that the project's potential environmental impacts are significant. Rather, it was dictated by the PSCW's rules that require an EIS for any project involving the construction of an "electric generation facility fueled by coal." The EIS considered background and regulatory requirements, costs and financing issues, the need for baseload capacity in Southeastern Wisconsin, alternatives to the proposed project, fuel diversity perspectives, the proposed sites and technologies, air emissions, water resources, solid and hazardous waste disposal and remediation, land resources, and community impacts. The EIS also provided a worst case analysis of the economic and environmental impacts that could result from the construction of a new power plant and its associated facilities. The EIS, however, was not an agency decision about the project and did not make recommendations about approval. The EIS was just one step in the process. Public and technical hearings followed in August and September of 2003. The agencies gave careful consideration to the more than 270 individuals that provided written comments on the ERGS draft EIS. In November 2003, the PSCW issued an order approving parts of the proposed project. The Commission:
On November 29, 2004, a Dane County Circuit Court vacated the PSCW's approval of our project and sent the case back to the Commission for additional proceedings. While we were disappointed with the decision, we were encouraged that the Court reaffirmed the need for the power and upheld the sufficiency of the state EIS. The PSCW, DNR, and Wisconsin Energy filed motions for direct, expedited appeal of the decision with the Supreme Court of Wisconsin. On January 5, 2005, the Supreme Court of Wisconsin granted the motion in a 5-1 vote. Briefs were filed in February and oral arguments were held on March 30, 2005. On June 28, 2005, the Supreme Court of Wisconsin reversed the Dane County Circuit Court's November 2004 decision and reinstated the Public Service Commission's final decision and order in all respects involving construction of the Oak Creek Power Plant expansion. It was a 4-2 decision with Justice Crooks not participating. Justice Bradley dissented and was joined by Chief Justice Abrahamson. Air Permit In February 2005, a Wisconsin Administrative Law Judge issued a decision affirming the DNR’s issuance of the Air Pollution Control and Construction Permit. In the decision, the Judge found that DNR did not err on any of the grounds raised by the opponents. Summary of the findings include:
On February 22, 2005, Clean Wisconsin and S.C. Johnson filed a lawsuit with the Dane County Circuit Court seeking judicial review of that decision. The Dane County Circuit Court dismissed on Sept.16, 2005, the appeal of an administrative law judge's decision, affirming the DNR’s issuance of the Air Pollution Control and Construction Permit for the Oak Creek expansion. All parties to this action agreed to the dismissal, including Clean Wisconsin and the Sierra Club. This dismissal is the final resolution of all legal challenges to the WDNR air permit. Chapter 30 Permit
In March 2005, the Dane County Circuit Court dismissed an appeal of the Chapter 30 permit based on improper filing procedures by S.C. Johnson and Sierra Club. The opponents have filed an appeal seeking review of the Court’s decision to dismiss. Wisconsin Pollutant Discharge Elimination System (WPDES) Permit On April 26, 2005, Clean Wisconsin and SC Johnson filed a lawsuit with the Dane County Circuit Court challenging the DNR’s decision to reissue a WPDES permit. Also, on May 12, 2005, DNR granted the request for a contested case hearing filed by Clean Wisconsin, Sierra Club, and several individuals. In Sept. 2005, the challenge filed with Dane County Circuit Court was dismissed. The DNR’s contested case hearing regarding the permit is scheduled for early March 2006. Army Corps of Engineers Permit Opponents have the option to challenge the Army Corps permit in federal court. |
||||||
Overview | Projects | Regulatory Documents | News | Q&A | Links | Contact Us Home | Top of page This site is best viewed with Netscape 4.0+ or Internet Explorer 4.0+ |